The first phase of the Cebu Bus Rapid Transit (CBRT) is estimated to be almost 60 percent complete as of Friday, February 16, 2024, and it is scheduled to be finished by early July 2024. CBRT manager Norvin Imbong confirmed this saying the phase 1 of the project is expected to conclude by early July 2024. Regarding phases 2 and 3, Imbong said they are working on obtaining the necessary approvals to commence the bidding process. Imbong personally conducted an on-site inspection on Friday to assess the progress of ongoing civil works related to the removal and transfer of skywalks affected by the CBRT project. He was accompanied by Councilor Jerry Guardo, chairman of the committee on infrastructure. It was reported that Councilor Nestor Archival expressed doubts about the completion timeline of CBRT following an executive session held to address its delays. On February 7, Archival sponsored a resolution following Councilor James Anthony Cuenco's privilege speech on January 10, 2024, highlighting issues surrounding the CBRT project.
The first phase of the Cebu Bus Rapid Transit ( CBRT ) is estimated to be almost 60 percent complete as of Friday, February 16, 2024, and it is scheduled to be finished by early July 2024 . CBRT manager Norvin Imbong confirmed this saying the phase 1 of the project is expected to conclude by early July 2024 . Regarding phases 2 and 3, Imbong said they are working on obtaining the necessary approvals to commence the bidding process .
Imbong personally conducted an on-site inspection on Friday to assess the progress of ongoing civil works related to the removal and transfer of skywalks affected by the CBRT project. He was accompanied by Councilor Jerry Guardo, chairman of the committee on infrastructure. It was reported that Councilor Nestor Archival expressed doubts about the completion timeline of CBRT following an executive session held to address its delays. On February 7, Archival sponsored a resolution following Councilor James Anthony Cuenco's privilege speech on January 10, 2024, highlighting issues surrounding the CBRT project
Cebu Bus Rapid Transit CBRT Completion Phase 1 July 2024 Approval Bidding Process Civil Works Skywalks Delays Doubts Resolution Issues